Projects Executed
Details of major projects/works executed
Please scroll/drag below block to view whole data
Sr. No. | Name of Projects / Works | Details of Project / Work | Cost (Rs. In lakh) | Year of Execution |
---|---|---|---|---|
Vehicle Service Station Complex at Rudarpura | This World bank aided project was executed for Health Department of SMC | 35.00 | 1993 | |
Transfer Station Complex at Anjana | This World bank aided project was executed for Health Department of SMC | 60.00 | 1993 | |
Singanpore Weir cum Causeway Project | The cell has carried out major role in co-ordination between Hazira Area Industries Association (HAIA) and SMC for this project. The project was executed and financed by the HAIA. and handed over to the SMC for operation and maintenance. The project has proved to be boon to Surat City. Surat City has flourished tremendously in terms of population and industries during past decade. The Corporation provides drinking water to citizens of Surat from the reservoir of Weir. HAIA also draws water for their industrial requirement. It is needless to say these mega industries have flourished very well and have enhanced prosperity and development in the region. Tidal silting and pollution brought along with tides have been controlled in the river. Ground water salinity ingress in the areas up stream of weir has been reduced considerably. Tidal erosion of river banks also controlled | 3500 | 1992-1995 | |
RCC double box for storm drain at Rander | To dispose storm water from Rander area of the City | 40.00 | 1995 | |
Control Tower Building at Singanpore Weir | This building was constructed for the requirement of Weir cum Causeway | 14.00 | 1995 | |
High mast tower for lighting at Singanpore | To illuminated causeway road this high mast towers were erected on both entry of causeway | 16.00 | 1995 | |
Construction of Flood Protection Gates (22 Nos) on outlets of different storm water drains leading to river Tapi | Total gate locations -15 Works were completed within 3 months. Cast Iron manually operated vertical sliding gates. Normally these gates are kept open, but at the time of heavy floods in the river gates are closed to prevent the entry of flood water in to the city. | 210.00 | 1999 | |
Construction of earthen embankment at Village Tunki | As a part of Flood protection scheme 725 m long earthen embankment with rubble pitching | 136.00 | 2000 | |
Construction of Sluice regulator at Village Tunki | As a part of Flood protection scheme Sluice Regulator on natural creek near Barimata- Tunki was constructed | 214.00 | 2000 | |
Construction of flood gate structure for Singanpore STP and storm drain at Bharimata | For facilitating discharge of Singanpore sewage treatment into river and to prevent flood water entering into storm box drain of Singanpore area a composite structure was designed and constructed at Bharimata | 131.00 | 2013 | |
Temporary flood protective works at various places | These works were executed to protect existing bank of river against flood damage | 178.00 | 2004-2005 | |
Bank Protection work at Singanpore | Earth embankments with Rubble pitching in GI Gabion wires to protect river flood entering in to City area | 1000.00 | 2006 | |
Bank Protection work at Rander Phase-1 | Earth embankments with Rubble pitching in GI Gabion wires to protect river flood entering in to City area | 1635 | 2006 | |
Bank Protection work at Rander Phase-2 | Earth embankments with Rubble pitching in GI Gabion wires to protect river flood entering in to City area | 796.21 | 2009 | |
Bank Protection work at Rander Phase-3 | Earth embankments with Rubble pitching in GI Gabion wires to protect river flood entering in to City area | 244.55 | 2009 | |
Bank Protection work at Bharimata Phase-1 | Earth embankments with Rubble pitching in GI Gabion wires to protect river flood entering in to City area | 1570 | 2006 | |
Bank Protection work at Bharimata Phase-2 | Earth embankments with Rubble pitching in GI Gabion wires to protect river flood entering in to City area | 1502.35 | 2009 | |
Preparation of flood Inundation and flood prediction map of Surat City | After 2006 flood, inundation map of Surat city is prepared. The work includes taking contour survey and H.F.L. at various location in the Surat City and their by examining flooded area. Preparation of prediction Map for different discharge from Ukai and there by predicting probable flood level at diff. location s in thecity | 2010 | ||
Construction of River Embankment Road from Amroli Bridge to BharimataKotar No.7 on the left bank of river Tapi | River Embankment having length of 10 Km. and width of about 5.00 Mt. Asphalt grouted Road for Pedestrian and recreation purpose of the citizens. This benefit to about 1.50 lac of population of Ashwanikumar, Ved, Dabholi, Katargam, Tunki, Singanpore area of the city | 303.00 | 2012 | |
Construction of sluice regulator structure on VarachhaKhadi near Water Works | Structure designed to withstand a flood of 8.0 lac cusecs. There are 4 Nos of 4.0 m x 4.0 m size electrically operated gates. This will relief about 2.25 lac population of Nana Varachha, Kapodra, Simada, Sarthana etc areas during flood situation | 680.00 | 2013-14 | |
Reinstatement of Apron at Weir cum Causeway, Singanpore | Disturbed Apron during flood-2006 are being reinstated at RL + 3.0. | 640.00 | 2014 | |
Raising of Retaining Wall work at Weir cum Causeway | As per suggestions from Irrigation Circle, Surat, the embankment beside control room on left and right bank raised from RL+14.0 to RL+16.0 by constructing RCC Retaining wall. | 359.00 | 2014 | |
Construction of Sluice Regulator Structure at ChhaprabhathaKhadi on the right bank of the River Tapi | Structure design to withstand a flood of 10.0 lac casecs. These will relief about 2.00 lac population of the Amroli, Chhaprabhatha, Kosadetc areas during flood situation. | 1010.00 | 2016 |