(3) Water Supply System for New South-East Zone area of Surat Municipal Corporation:
- Sanctioned Amount: Rs. 20109.67 Lacs
- Target Completion as per DPR – March 2012
- Expenditure till March 2010 – 1357.56 Lacs
Package | Work | Brief Title of Tender Package / Work | Estimated - NURM Amount Rs. in Lacs |
---|---|---|---|
No. | |||
1 | Construction of intake well, pumphouse, approach bridge | ||
1 | 370 mLd capacity intake well, pumphouse, approach bridge and pipeline works near Sarthana | ||
Civil works | 1296.40 | ||
Control Room and sub station at intake well | 27.23 | ||
2 | Construction of WTP | ||
1 | 78 mLd capacity Water Treatment Plant at Dindoli | 1679.18 | |
3 | Construction of UGSR & ESR at WDS. | ||
1A | Construction of treated water sump & WDS at Dindoli(90 Lac Liters) | 419.93 | |
1B | Construction of treated water sump & WDS at Jiyav (34 Lacs Liters) | 222.48 | |
1C | Construction of treated water sump & WDS at Bamroli (46 Lacs Liters) | 251.67 | |
1D | Construction of treated water sump & WDS at Godadara (39 Lacs Liters) | 235.38 | |
2A | Construction of ESR- 5 Nos for Dindoli WDS, 12 Lacs-3, 21 Lacs- 1, 15 Lacs- 1 No | 707.91 | |
2B | Construction of ESR - 3 Nos. for Jiyav WDS, 12 Lacs-2, 15 Lacs-1 No. | 389.68 | |
2C | Construction of ESR - 5 Nos. for Bamroli WDS, 12 Lacs- 4 Nos., , 15 Lacs-1 No. | 630.15 | |
2D | Construction of ESR - 3 Nos. for Parvat WDS, 18 Lacs-1, 12 Lacs-2 Nos. | 407.44 | |
4 | Mechanical and Electrical works at intake wells and booster houses. | ||
1 | Mechanical & Electrical works for Intake | 436.97 | |
2 | Mechanical & Electrical works - WDS-1 | 386.43 | |
3 | Mechanical & Electrical works - WDS-2 | 175.52 | |
4 | Mechanical & Electrical works - WDS-3 | 210.21 | |
5 | Mechanical & Electrical works - WDS-4 | 178.96 | |
5 | Raw water Trunk Mains, Rising Mains & Transmission Pipelines | ||
1 | Raw Water Trunk Main from Intake well to WTP at Dindoli | 4881.77 | |
6 | 1 | Treated Water Transmission main from WTP at Dindoli to WDS-SE2 , WDS-SE3 & WDS-SE4 | 2256.37 |
2 | Rising Mains from all WDS to ESRs | ||
(i) | Rising Main from WDS-SE1 to proposed ESR- SE1,SE2&SE3 | 341.37 | |
(ii) | Rising Main from WDS-SE2 to proposed ESR-SE4 & SE5 | 365.84 | |
(iii) | Rising Main from WDS-SE3 to proposed ESR-SE6,SE7 & SE8 | 255.73 | |
(iv) | Rising Main from WDS-SE4 to proposed ESR-SE9 & SE10 | 123.75 | |
7 | 1 | Distribution network etc. | |
1 | Procurement of DI pipes- K7 class | 3427.44 | |
2 | Crossing of Railway, canal & khadi etc. | 553.45 | |
3 | Surge Control Device & chamber | 22.77 | |
4 | Water meters | 225.63 | |
Total | 20109.67 |