Construction of " Shri Ramkrishna Paramhans " FOB on Katargam main road.

01 Location : Katargam main Road
02 River/ Nala/ Creek : Fly Over Bridge
03 Lane : Three Lane
04 Year of Construction : Completed 2015
05 Cost : Rs.66,75,88,365=12 Paise
06 Details of Bridge :  
  (i) Length of Bridge
(Between ends of Decking)
: Main bridge� 1142.00 mt.
Down (Exit) Amroli Side - 328.84mt.
Sumul Dairy side Entry Ramp = 351.00 mt.
  (ii) Number of Span : 78 nos. (main bridge), 27 nos. (exit ramp) and 27
nos. (Sumul dairy side entry ramp)
  (iii) Span Length :  6mt. to 50mt. (varing)
  (iv) Carriage Way : 5.35 + 5.35 ( Up & Down )
  (v) Length of R.C.C.
Approaches &Returns
: --------
07 (i) Design Discharge : --------
  (ii)  Design H.F.L. : --------
  (iii) Type of Bridge : Fly Over Bridge
  (iv) F.R.L. : Varies
08 Structural Details    
  (i) Foundation : Pile Foundation, Pile Cap
  (ii) Substructure : Single R.C.C Pier
  (iii) Superstructure : Solide slab, PSC BOX GIRDER, PSC I Girder With Deck Slab
  (iv) General Items : Crash barrier, wearing coat
09 Name of Contractor : Dineshchandra R.Agrawal Infrastructure Pvt Ltd., Ahmedabad
10 Name of Design Consultant : Multimedia Consultants Pvt. Ltd., Ahmedabad.
11 Name of PMC : Spectrum Techno Consultant Pvt Ltd., Navi Mumbai
12 Name of Proof Checking Consultant : SVNIT. And R & B Dept. (Design) Circle, Gandhinagar.