Construction of Fly Over Bridge at Kapodra Fire Station junction on Varachha main road, Surat. (Under JnNURM)

1. Location : In East zone area near Kapodra Fire Station junction on Varachha road, Surat.
2. River/ Nala/ Creek : Fly Over Bridge
3. Lane : 11 mts (three lane) Main bridge
      15 mts grade separators from city to Kamrej
4. Year of Construction : November- 2009
5. Cost : Rs.1004.58 Lacs
6. Funding under JnNURM Scheme    
  Sanctioned project cost : Rs. 932 Lacs
  Share of GoI (50%) : Rs. 466 Lacs
  Share of GoG (20%) : Rs. 186.40 Lacs
  Share of SMC (30%) : Rs. 279.60 Lacs
6. Details of Bridge :  
7. (i) Length of Bridge (Between ends of Decking) : 315 mt.
  (ii) Number of Span : 9 nos.
  (iii) Span Length : 35 mt.
  (iv) Carriage Way : (i) 11.0 mt. fly over (form Kamrej to Surat) (ii) 14.0 mt. Grade seperator (from Surat to Kamrej)
  (v) Length of R.C.C. Approaches &Returns : (i) 76.0 mt. ( Towards Kamrej) (ii) 120.0 mt. ( Towards Surat)
  (Vi) Subway for pedestrian crossing : 34.0 mt. Length 5.0 mt. Width 3.0 mt. Height
8. (i) Design Discharge : N.A.
  (ii) Design H.F.L. : N.A.
  (iii) Type of Bridge : Fly Over Bridge plus grade separator
  (iv) F.R.L. : N.A.
9. Structural Details    
  (i) Foundation : Open Foundation
  (ii) Substructure : Circular Pier
  (iii) Superstructure : PSC Box type girder and Deck slab
  (iv) General Items : R.E.Wall in approaches, RCC Box subway for pedestrian crossing at road level.
10. Name of Contractor : Sona Builders, Unjha.
11. Name of Design Consultant : S.N.Bhobe & Associates, Pvt. Ltd., Navi Mumbai.
12. Name of Project Management Consultant : S.N.Bhobe & Associates, Pvt. Ltd., Navi Mumbai.
13. Name of Third Party Inspecting agency : Certifications Engineers International Ltd., New Delhi.
14. Name of Proof Check Consultant : Sardar Vallabhbhai National Institute of Technology, Surat.