1.
|
Location
|
:
|
In East zone area near Kapodra Fire Station junction on Varachha road, Surat.
|
2.
|
River/ Nala/ Creek
|
:
|
Fly Over Bridge
|
3.
|
Lane
|
:
|
11 mts (three lane) Main bridge
|
|
|
|
15 mts grade separators from city to Kamrej
|
4.
|
Year of Construction
|
:
|
November- 2009
|
5.
|
Cost
|
:
|
Rs.1004.58 Lacs
|
6.
|
Funding under JnNURM Scheme
|
|
|
|
Sanctioned project cost
|
:
|
Rs. 932 Lacs
|
|
Share of GoI (50%)
|
:
|
Rs. 466 Lacs
|
|
Share of GoG (20%)
|
:
|
Rs. 186.40 Lacs
|
|
Share of SMC (30%)
|
:
|
Rs. 279.60 Lacs
|
6.
|
Details of Bridge
|
:
|
|
7.
|
(i) Length of Bridge (Between ends of Decking)
|
:
|
315 mt.
|
|
(ii) Number of Span
|
:
|
9 nos.
|
|
(iii) Span Length
|
:
|
35 mt.
|
|
(iv) Carriage Way
|
:
|
(i) 11.0 mt. fly over (form Kamrej to Surat)
(ii) 14.0 mt. Grade seperator (from Surat to Kamrej)
|
|
(v) Length of R.C.C. Approaches &Returns
|
:
|
(i) 76.0 mt. ( Towards Kamrej) (ii) 120.0 mt. ( Towards Surat)
|
|
(Vi) Subway for pedestrian crossing
|
:
|
34.0 mt. Length 5.0 mt. Width 3.0 mt. Height
|
8.
|
(i) Design Discharge
|
:
|
N.A.
|
|
(ii) Design H.F.L.
|
:
|
N.A.
|
|
(iii) Type of Bridge
|
:
|
Fly Over Bridge plus grade separator
|
|
(iv) F.R.L.
|
:
|
N.A.
|
9.
|
Structural Details
|
|
|
|
(i) Foundation
|
:
|
Open Foundation
|
|
(ii) Substructure
|
:
|
Circular Pier
|
|
(iii) Superstructure
|
:
|
PSC Box type girder and Deck slab
|
|
(iv) General Items
|
:
|
R.E.Wall in approaches, RCC Box subway for pedestrian crossing at road level.
|
10.
|
Name of Contractor
|
:
|
Sona Builders, Unjha.
|
11.
|
Name of Design Consultant
|
:
|
S.N.Bhobe & Associates, Pvt. Ltd., Navi Mumbai.
|
12.
|
Name of Project Management Consultant
|
:
|
S.N.Bhobe & Associates, Pvt. Ltd., Navi Mumbai.
|
13.
|
Name of Third Party Inspecting agency
|
:
|
Certifications Engineers International Ltd., New Delhi.
|
14.
|
Name of Proof Check Consultant
|
:
|
Sardar Vallabhbhai National Institute of Technology, Surat.
|