(2) Water Supply System for New North Zone area of Surat Municipal Corporation:
- Sanctioned Amount: Rs. 16743.47 Lacs
- Target Completion as per DPR – March 2011
- Expenditure till March 2010 – 6715.36 Lacs (40%)
Package | Work | Brief Title of Tender Package / Work | Estimated - NURM Amount Rs. in Lacs |
---|---|---|---|
No. | |||
1 | Construction of intake well, pumphouse, approach bridge | ||
1 | 200 mLd capacity intake well, pumphouse, approach bridge and pipeline works near Motavarachha | ||
Civil works | 1107.99 | ||
Control Room and sub station at intake well | 21.05 | ||
2 | Construction of WTP | ||
1 | 32 mLd capacity Water Treatment Plant at Mota Varachha | 563.04 | |
2 | 90 mLd capacity Water Treatment Plant at Kosad | 1536.98 | |
3 | Construction of UGSR & ESR at WDS. | ||
1A | Construction of treated water sump & WDS at Mota Varachha (88 Lac Liters) | 279.05 | |
1B | Construction of treated water sump & WDS at E-Point (139 Lacs Liters) | 366.06 | |
1C | Construction of treated water sump & WDS at Kosad (45 Lacs Liters) | 212.30 | |
1D | Construction of treated water sump & WDS at Variav (54 Lacs Liters) | 233.92 | |
2A | Construction of ESR- 4 Nos for Mota Varachha WDS, 18 Lacs-1, 21 Lacs- 3 Nos | 816.96 | |
2B | Construction of ESR - 6 Nos. for E-Point WDS, 21 Lacs-1, 15 Lacs-5 Nos. | 1037.47 | |
2C | Construction of ESR - 3 Nos. for Kosad WDS, 21 Lacs-1, 15 Lacs-1, 18 Lacs-1 No. | 585.08 | |
2D | Construction of ESR - 3 Nos. for Variav WDS, 18 Lacs-1, 21 Lacs-2 Nos. | 611.52 | |
4 | Mechanical and Electrical works at intake wells and booster houses. | ||
1 | Mechanical & Electrical works - WDS-1 | 209.89 | |
2 | Mechanical & Electrical works - WDS-2 | 423.90 | |
3 | Mechanical & Electrical works - WDS-3 | 146.46 | |
4 | Mechanical & Electrical works - WDS-4 | 192.47 | |
5 | Mechanical & Electrical works for Intake | 413.60 | |
5 | All MS Trunk mains & Transmission Pipelines & Valves etc. | 2409.34 | |
1 | Procurement of Pipelines & Valves | ||
2 | Outer guniting of all MS pipes | ||
3 | Laying of MS trunk mains & transmission pipelines | ||
4 | Laying of 700 mm dia. DI pipeline for transmission pipeline from WTP at E-Point to WDS at Kosad & variav | ||
5 | Inner CM lining work of MS pipeline | ||
6 | 1 | Rising Mains from all WDS to ESR & Dist. Network of all WDS - DI Pipelines | 4423.39 |
2 | Crossing of Railway, canal & khadi etc. | 131.90 | |
3 | Misce. Works like compound wall etc. | 361.28 | |
4 | Water meters | 659.80 | |
Total | 16743.43 |