How Do I Get a Drainage Connection?
- Owner of the property should apply through drainage licensed plumber to the concern zone office along with drainage plan in a prescribed application form and copy of receipt of property tax of the year applied. This form can be had from the concern zone office.
- Zonal Officer will approve the drainage plan and grant permission for drainage connection within 15 days. Along-with application form, applicant shall have to pay the connection charges and road reinstatement charges as resolved by the General Board of Corporation.
Details of Connection Charges
Sr. No. | Details of Connection | Charges per Drainage Connection |
---|---|---|
1. | Vertical Development tenement | |
Three storeyed or more than three storeyed building. | Rs. 500/- per flat | |
2. | Horizontal development per 'Gala'(Unit) and Bungalow. |
Rs. 1,000/- per bungalow Rs. 500/- per "Gala"(Unit) |
3. | Processing House per connection. | Rs. 10,000/- + Rs. 3/- Sq.ft. |
4. |
For Hotel, lodging, Boarding House having (a) An area upto 250 sq.ft. (b) 250 sq.ft. to 500 Sq.ft. (c) An area exceeding 500 Sq. ft. |
Rs. 1,000/- Rs. 2.000/- RS. 5,000/- + Rs. 3/- per Sq.ft. |
5. | For Factories and Industries per connection (except processing house) | Rs. 4,000/- |
6. | For shops and office connection. | Rs. 1,000/- |
7. | Industrial Units, Hotel, Hospital. | |
(A) Latrine or chowkadi or for both the connection. | Rs. 4,000/- | |
8. | For "Chalis" | |
(A) Latrine or chowkadi or for both the connection. | Rs. 500/- |
- Applicant shall have to lay the drainage line as approved by Zonal Officer at his own cost through the licensed plumber.
- If the assessment value of the property is less than Rs. 1000/-, the applicant may avail free drainage connection.
- If any society/institution intends to lay drainage line in their own premises through corporation, the society/institution shall have to pay the 6 % supervision charges along with their contribution as stated below.
Contribution of Public and SMC
Complex | Public Contribution | SMC contribution |
---|---|---|
Residential Housing Society | 35 % | 65 % |
Industrial Society/Housing Board | 50 % | 50 % |
Industrial Estate | 65 % | 35 % |
Socially and Economically Backward class Society | 15 % | 85 % |
- The authorised person of society/institution shall have to apply to the drainage department with Rs. 5000/- as a deposit for preparing estimate along with three copies of sanctioned layout plan of society/institution.
- The Incremental Contribution charges shall have to be paid by the society/institute prior to getting facility.