Bridge across Kankara Khadi near South Zone Office (Revanagar)

1. Location From Surat Navsari Road to Revanagar
2. River/Nala/Creek Kankara khadi
3. Lane Four lane
4. Year of construction 1996-1997
5. Cost Rs.149.62 Lacs 
6. Details of Bridge  
  Length of Bridge  77 mtr.
  (ii) Number of span Seven
  (iii) Span Length 11 mtr.
  (iv) Carriage Way 2x7.5 mtr. + 1.20 mtr.wide footpath on both side each on two separate bridges.
  (v) Length of Returns Right side -10.25 mtr.
7. (i)Design Discharge 1050 Cumecs
  (ii) Design H.F.L. R.L.6.40 mtr.
  (iii) Type of bridge Submersible bridge.
  (iv) F.R.L. R.L.(-)18.0 mtr. piers
    R.L.14.00 mtr.abutments
8. Structural Details :  
  (i) Foundation. R.C.C. bored cast in situ piles 1200 mm dia 23.00 deep.
  (ii) Substructure R.C.C. piles extended to directly suport deck.
  (iii) Superstructure R.C.C. solid slab deck simply supported on elastomeric bearings.
  (iv) General Items Post and pipe rails. The bridge also has provision for carrying 2 Nos. 1000 mm dia water supply mains.
9. Name of Contractor M/s. Sona Builders, Surat.
10.  Name of Consultant Multi Media Consulting Engineers, Ahmedabad.